LABOURS ESTIMATE


ESTIMATION OF LABOURS FOR VARIOUS WORK ITEMS

For a Project Engineers/Site Engineers/Project Manager, it is very important to assess the number of workers required for doing a particular work so as to save money and time and to avoid over allocation or less allocation of resources. And knowing the labours requirement, it helps Engineers to assess the total quantity of works that they can do in a day and hence the time required to complete the given task as well. So let us take a look at some of the important tasks and approximate requirements of labours to do a task. Labours estimates are approximate and it may vary as per the work quantity and size of project works and work conditions apply. The following estimation of labours requirement for a particular item of works for 8 working hours.

                  Items                    Quantity
1. Concrete in Foundation.:- 10 m3
Head Mason 1/4,
Mason 2, Labour 20


2. R.C.C. M – 15 grade. 10 m3
Head Mason 1/2, Mason 3, Labour 23

Note: For each additional storey, the strength should be increased by 6 nos. for the volume of 10 cu.m to lift the materials.

3. Supplying, fitting, fixing and removing shuttering & staging. For 7 m2
Carpenter 1, Labour 2

4. Reinforcement for R.C.C. work including cutting, bending and placing in position 100 kg.
Bar binder (Blacksmith/fitter) 1, Labour 1

5. Damp proof course.for 100 m2
Head Mason 1/2, Mason 5, Labour 6

6. First class brickwork in 1:6 in the superstructure. 10 m3
Head Mason 1/2, Mason 9, Labour 18, Bhisti 2

7. Brick on edge flooring with cement Mortar (1:3). 100 m2
Head Mason 1/2, Mason 10, Labour 14, Bhisti 1

8. Ironite flooring (40mm thick). 100 m2 Head Mason 1, Mason 24, Labour 27, Labour for Scrubbing 3

9. C.G.I sheeting on roof 10 m2 Carpenter 1, Fitter (Blacksmith) 1/2, Labour 2

10. C.I. rainwater pipe fixing. 9 m
Mason 1/2, Labour 2.5

11. 12mm thick cement plaster on brickwork in 1:6. 100 m2
Head Mason 1, Mason 10, Labour 14, Bhisti 1

12. Ruled pointing (1:3). 100 m2
Head mason 1/2, Mason 10, Labour 9, Bhisti 1

13. Whitewashing primer coat and 2 finished coats to new plaster. 100 m2
Painter 1/2, Labour 2

14. Dry Distemper 100 m2 Painter 8.5, Labour 5.5

15. Plastic Emulsion paint on new work. 100 m2
Painter 5.5, Labour (Helper) 5.5

16. Primer coat on woodwork/ steelwork. 100 m2
Painter 2.5, Labour (Helper) 2.5

17. Panting two coats over priming coat for new woodwork/steelwork. 100 m2
Painter 5.5, Labour (Helper) 5.5

18. Demolishing cement concrete (1:2:4/1:3:6) including lead up to 50m. 10 m3 Labour 23

19. Demolishing R.C.C. work including lead up to 50m. 10 m3
Labour 33.5

20. Demolishing Brickwork in cement mortar including stacking of serviceable material and disposal of unserviceable materials within a lead of 50m. 10 m3 Labour 19.5

21. Removing mortar and cleaning bricks and stacking cleaned bricks. 10 m3
Mason 6, Labour 25

22. Dismantling doors & windows including framing, stacking of material.
1 no. Mason 1, Labour 0.20

23. Supplying and fixing 12mn/15mm dia G.I. pipe with G.I. fittings and M.S. clamps including cutting holes in walls and making good the same 100 r.m.
Fitter 7, Labour (Beldar) 6

24. Supplying, fitting and laying 25mm G.I pipes with G.I. fittings including trenching and refilling of external work 100 r.m.
Fitter 1, Labour 8

25. Laying, fitting and fixing 100 mm dia G.I. pipes including testing of joint, trench cutting for pipe laying up to a depth of 90 cm. and refilling, dressing etc. 20 r.m.
Fitter 1.5, Labour 13

26. Supplying, laying, joining 100 dia stoneware pipes with cement mortar 1:1 (excluding earthwork etc.). 15 r.m...
Mason 1, Labour 2

27. Wash Basin with C.I. brackets, brass taps, brass plug with brass chain, waste pipe Including cutting walls and making good the same. 1 no.
Plumber 1, Mason 1/2, Labour 1

28. Sink. 1 no.
Plumber 1/2, Mason 1/2, Labour 1

29. 9″ thick brick flat soling filled with local sand. 10 m2
Labour 1

30. Earthwork for roads including cutting, loading, unloading, carrying & dressing. 10 m2
Labour 4

31. Stone soling for roads including packing with smaller stones manually. 10 m3
Labour 7

32. Stone soling for roads including packing with smaller stones With steam roller. 20 m3
Labour 7.



Thanks...