P.C.C IN FOUNDATION TRENCH:-

3'0"x 3'0" x 0.5 x 9 Nos                    =          40.5 cft


Material required :

Cement                       =          7 bags

sand                            =          27 cft

11/2" jally                   =          35 cft

R.C.C FOR COLUMN UP TO 5 FEET HEIGHT:-

9"x 9"x5'0"x9 nos     =          25.31 cft

Material required :

cement            =          5 bags

sand                =          17 cft

3/4 jally           =          22 cft

R.C.C. FOR COLUMN FOOTING : -

3'0" x 3'0"x 0.75 x 9 nos

Material Required :

cement            =          10 bags

sand                =          40 cft

3/4 jally           =          51 cft

TIE BEAMES ALL ROUND AND INSIDE : -

22'3" x 9" x 9" x 3 nos          =          37.54 cft

21'0" x 3 Nos x 9" x 9"         =          35.4375

Total                                       =          72.95 cft
Material Required :
Cement           =          14 nos

Sand               =          40 cft

3/4 jally           =          52 cft

9" wall all round:-

22'3" x 9" x 9'0" x 2             =          310 .54  cft

21'0" x 9" x 9'0" x 3             =          425.25 cft

Material required :

Cement                       =          58 bags

Sand                           =          478 cft

Brick                           =          18,000 Nos

INNER WALL PLASTERING :-


23'0" x 9'0" x 2         =          414 cft

21'0" x 9'0" x 4         =          756 cft

Total                           =          1170 cft

MATERIAL REQUIRED :

Cement                       =          47 Nos

Sand                           =          760 cft

EXTERNAL WALL PLASTERING:-


23'0" x 9'0" x 2         =          414 cft

21'0" X 9'0" x 2         =          378 cft

Total                           =          792 Cft
MATERIAL REQUIRED :

Cement           =          32 Nos

sand                =          514 Cft

R.C.C roof of 1:2:4

23'0" x 21'0" x 0.375            =          182 cft

MATERIAL REQUIRED :

cement            =          39 nos

sand                =          313 cft

3/4 jally           =          410 cft



Eastimation For Additional Work :-

P.C.C in foundaction Trench : -

3'0" x 3'0"x 0.5x12               =          54 cft

Material required :-

Cement                       =          5 Nos

Sand                           =          36 cft

1 1/2 Jally                   =          46 cft

R.C.C Column Up to 5 feet height : -

9" x 9" x 5'0" x 12 Nos                     =          33.75 Cft

Material required : -

Cement                       =          8 Nos

Sand                           =          22 Cft

3/4 Jally                      =          29 Cft




R.C.C For column Footing:-

3'0" x 3'0"x0.75 x 12            =          81 cft

Material Required : -

Cement           =          14 Nos

Sand               =          53 Cft

3/4 Jally          =          69 Cft


Tie Beams all round and inside :-

8'0" x 9" x 9" x 6                  =          27 cft

21'0" x 9" x 9" x 2    =          23.625 Cft

20'9" x 9" x 9" x 2    =          23.34375 cft

9'6" x 9" x 9" x 2                  =          10.6875 Cft

Total                                       =          84.65625 Cft

Material Required : -

Cement                       =          19 Nos

Sand                           =          56 Cft

3/4 Jally                      =          72 Cft

9" Wall all round:-

8'9" x 9" x 9'0" x 4   =          236.25 Cft

21'0" x 9" x 9'0" x 2 =          283.5 Cft

9'6" x 9" x 8'0" x 2   =          114 . 0 Cft

20'9" x 9" x 8'0"x 2  =          249.00 Cft

Total                                       =          882.75 Cft



Material required : -

Cement                       =          36 Nos

Sand                           =          265 Cft

Brick                           =          11035 Nos

4 1/2 wall inside : -

8'0" X 9"0" X 2                     =          144 Sft

4'7 1/2 " x 3 x 8'0"    =          111 sft

4'0" x3 x 8'0"             =          96 sft

Total                                       =          351.00 Sft

Material Required : -

Cement                       =          8 Nos

Sand                           =          54 Cft

Brick                           =          1790 Nos

Inner wall Plastering : -

8'0" X 9'0" X 8                      =          576

20'9" X 8'0" X 2                    =          332

9'6" X 8'0" X 2                      =          152

4' 71/2" X 8'0" X 6                =          222

Total                                       =          1282

Material Required :-

Cement           =          23 Nos

Sand               =          167 Cft





External Wall Plastering:-

8'0" x 11'0" x 4                     =          352

21'0" x11'0" x 2                    =          462

20'9" x 9'0" x 2                     =          373.5

9'6" x 9'0" x 2                       =          171.00

Total                                       =          1358.50 sft

Material Required :-

Cement                       =          21 Nos

Sand                           =          177 Cft

R.C.C Roof Slab:-

8'0" x 21'0" x 0.375 x 2        =          126.00 Cft

20'9" x 9'6" x 0.375              =          73.92 Cft

Total                                       =          199.92  Cft

Material Required :-

cement                        =          34 nos

Sand                           =          130 cft

3/4 jally                       =          169 cft

P.C.C in Flooring : -

8'9" x 21'0" x 2         =          367.5

20'9" x 9'6"    =          197.125

Total               =          564.625 Cft



Material Requiired :-

Cement                       =          46  Nos

Sand                           =          368 Cft

11/2 Jally                    =          480 Cft


TOTAL MATERIAL REQUIREMENT :

Cement                       =          212 nos x 185                         =          39220

Sand                           =          2189 cft x 12                           =          26268

Brick                           =          18000 x 2.40                           =          43200

11/2 Jally                    =          135 cft x 20                             =          2700

3/4 Jally                      =          462 cft x 28                             =          12936

Steel required for beam,column& roof

8 mm                           =          210 kg x 30                             =          6300

10 mm                         =          112 kg x 30                             =          3360

6 mm                           =          180 kg x 30                             =          5400

Cement                       =          214 nos x 185 rs                     =          39,590 Rs

Sand                           =          1328 Cft x 12 Rs                    =          15936 Rs

Brick                           =          12,825 x 2.4 Rs                       =          30780 Rs

3/4 Jally                      =          340 Cft x 29 Rs                      =          9860 Rs

1 1/2 Jally                   =          526 Cft x 20 Rs                      =          10520 Rs

Steel required for beam,column& roof

10 mm                        =          224 Kg x 30 Rs                       =          6720 Rs

8 mm                           =          450 Kg x 30 Rs                       =          13500 Rs

6 mm                           =          400 Kg x 30 Rs                       =          12000 Rs

Mazon                        =          L.S                                          =          57600 Rs

Helper's                      =          L.S                                          =          35800 Rs

Door's & windows    =          L.S                                          =          40000 Rs

Centering Labour     =          L.S                                          =          35000 Rs

Water Tank               =          L.S                                          =          12000 Rs

Plumbing Work        =          L.S                                          =          20000 Rs

White washing           =          L.S                                          =          30000 Rs

Total                                                                    =       508690.00 Rs

           



Post a Comment

Previous Post Next Post